Street Work Updates

The following are updates on current street work in the City of Watertown:

Posted 05/30/2017:
Curb and gutter will be poured on West Street today.

Posted 05/18/2017:
Seal coating will begin in the city on Tuesday (05/23/2017), weather permitting.  This project is expected to take 1-2 weeks to complete. In the case of inclement weather, this timeline may be exceeded. The seal coating process extends the life of the paved surface by providing a protective layer from moisture, chemicals, and the sun.  The following is a complete list of streets affected by this project:

Street Name

At:

Towards:

Length

Width

Sq. Yards

 

Anne Street

Labaree St.

Highland St.

1,056

32

3,755

 

Jones Street

First St.

Second St.

300

36

1,200

 

Second St.

Third St.

260

34

982

 

Third St.

Fourth St.

260

30

867

 

Fourth St.

Fifth St.

264

30

880

 

Fifth St.

Sixth St.

264

30

880

 

Eighth St.

Ninth St.

422

30

1,407

 

Ninth St.

Tenth St.

264

30

880

 

Tenth St.

Dewey Ave.

240

30

800

 

Milford St.

Bernard St.

Johnson St.

528

28

1,643

 

N. Fourth St.

E. Main St

Jones St.

528

36

2,112

 

N. Ninth St.

E. Main St

Jones St.

581

28

1,808

 

S. Washington

Emmet St.

E. Main St.

422

27

1,266

 

Timber Ridge Trail

Bare Pvmt

Schumann Dr.

700

32

2,489

 

Utah Street

Boomer St.

Termini

560

29

1,804

 

Bernard St.

Milford St.

S. Montgomery St.

800

40

3,556

 

E. Madison St.

N. First St.

N. Fourth St.

792

38

3,344

 

N. Fourth St.

N. Sixth St.

528

35

2,053

 

N.Sixth St.

N. Seventh St.

264

30

880

 

N. Seventh St.

N. Eighth St.

264

26

763

 

Elizabeth St.

Center St.

Termini

1,056

26

3,051

 

N. Seventh St.

E. Main St

E. Madison St.

317

26

916

 

N. Sixth St.

E. Main St

E. Madison St.

264

32

939

 

N. Fifth St.

E. Main St

E. Madison St.

317

36

1,268

 

E. Cady St.

N. Second St.

N. Third St.

158

28

492

 

N. Third St.

N. Fourth St.

211

29

680

 

N. Fourth St.

N. Sixth St.

528

28

1,643

 

N. Sixth St.

N. Eighth St.

528

26

1,525

 

N. Eighth St.

Dewey Ave.

845

28

2,629

 

N. Third St.

E. Main St.

Cady St.

792

38

3,344

 

Cole St.

N. Second St.

N. Fourth St.

581

28

1,808

 

N. Fourth St.

N. Sixth St.

528

26

1,525

 

N. Eighth St.

Dewey Ave.

792

26

2,288

 



Posted 04/24/2017:
Contractors have started their work on West Street today.  They are expected to continue their work at that location for several weeks.


2017 Project Streets

Reconstruction

     

Street

At

Towards

Segment Length in Feet

Clay Street

W. Spaulding St.

James St.

1637

West Street

Hunter Oak Blvd.

Benton Street 

2550

       

Resurface

     

Street

At

Towards

Segment Length in Feet

Edgewater Court

W. Leonard St.

Termini

581

Stone Street

Clay St.

Termini

475

Silver Drive

N. Water St.

Amber Ln.

475

W. Arcade St.

N. Water St.

Clay St.

317

N. Maple Street

Jones Street

E. Main St.

1161

N. Concord Avenue

Jones Street

E. Main St.

1320

Hart Street

Dakota Street

S. Third St.

370

Mary Street

Neenah Street

S. Third St.

792

Ruth Street

N. Concord Ave

Dewey Ave

800

Jones Street

N. Concord Ave

Dewey Ave

792


This information will be updated as construction progresses.  All schedules may change due to weather delays or contractor availability. 

The Watertown Street Department works 4-day work weeks in the summer months.  City construction crews do not work Fridays.

If you have any questions, please feel free to contact the Street Department at (920) 262-4080 or the Engineering Department at (920) 262-4047.